page 1Question

The reflected ceiling plan shows an exposed structure ceiling at the loading dock, and specification 21 13 13 paragraph 2.06 requires concealed heads only in areas with a finished ceiling. The same paragraph requires dry pendent heads in the loading dock. Please confirm that exposed upright heads on a dry system are intended at the loading dock rather than concealed heads.

Cross references

DirectionRelationDocumentNote
this →references21 13 13 Wet-Pipe Sprinkler SystemsRFI-038 cites 21 13 13 paragraph 2.06