Corbel

BRK-2201 · Brickell Bay Tower

The project record

23 documents, 640 pages, 53 indexed passages. Every answer Corbel gives comes from one of these pages.

Specification

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
03 30 00Cast-in-Place Concrete rev 1StructuralJun 7, 2025Kessel Structural Engineers3444
07 52 00Modified Bituminous Membrane Roofing rev 2ArchitecturalJul 30, 2025Ardent Architects1842
07 84 00Firestopping rev 1ArchitecturalAug 3, 2025Ardent Architects1221
08 44 13Glazed Aluminum Curtain Walls rev 3ArchitecturalAug 13, 2025Ardent Architects2642
14 21 00Electric Traction Elevators rev 1Vertical TransportationJul 2, 2025Lindeman Vertical2931
21 13 13Wet-Pipe Sprinkler Systems rev 1Fire ProtectionJun 22, 2025Corso Fire Engineering2131
26 05 19Low-Voltage Electrical Power Conductors and Cables rev 2ElectricalJul 22, 2025Ferro Electrical Design1621

RFI

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
RFI-014Parapet height at north elevation less than specified base flashing heightArchitecturalJun 1, 2026Juniper Roofing323
RFI-021Curtain wall deflection criteria at double height lobbyStructuralJun 9, 2026Cordova Glass Systems322
RFI-027Hot weather placement plan for level 14 slab pourStructuralJun 26, 2026Quarry Ridge Concrete322
RFI-033Aluminum feeder conductors proposed as a substitutionElectricalJul 15, 2026Everglade Electric322
RFI-038Concealed sprinkler heads in the loading dockFire ProtectionJul 27, 2026Windward Fire Protection311
RFI-041Curing compound compatibility with resilient flooring on levels 3 through 8ArchitecturalAug 3, 2026Quarry Ridge Concrete321
RFI-046Firestop engineering judgement for clustered conduit penetrationElectricalAug 17, 2026Everglade Electric321

Submittal

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
SUB-033000-03Concrete mix designs, structural slabs rev 1StructuralJul 31, 2025Quarry Ridge Concrete211
SUB-075200-01Roofing system product data and warranty form rev 1ArchitecturalAug 31, 2025Juniper Roofing321
SUB-084413-02Curtain wall shop drawings, east and north elevations rev 1ArchitecturalOct 29, 2025Cordova Glass Systems322
SUB-142100-01Elevator equipment data, bank A rev 1Vertical TransportationNov 29, 2025Halcyon Elevator321

Meeting minutes

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
OAC-2026-31Owner Architect Contractor meeting number 31GeneralAug 24, 2026Vantage Construction Group732

ASI

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
ASI-006Revised parapet detail, north elevation rev 0ArchitecturalJun 13, 2026Ardent Architects423

Change order

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
CO-014Parapet raise, north elevationArchitecturalJul 7, 2026Vantage Construction Group322

Inspection report

NumberTitleDisciplineIssuedAuthorPagesIndexedLinks
INSP-2026-118Special inspection report, level 14 slab placementStructuralJun 29, 2026Ballast Testing Laboratories521
INSP-2026-131Floor flatness survey, levels 3 through 8ArchitecturalAug 12, 2026Ballast Testing Laboratories921