Ambient temperature at start of placement 88 degrees Fahrenheit rising to 93 degrees Fahrenheit at 14:00. Concrete temperature at the point of placement measured between 84 and 89 degrees Fahrenheit across nine trucks. Calculated evaporation rate reached 0.21 pounds per square foot per hour between 12:30 and 14:15. A written hot weather placement plan dated six business days before placement was on site and was followed, including fogging and immediate application of curing.
← The project record
Inspection report
INSP-2026-118
Special inspection report, level 14 slab placement
insp_118.pdf · 5 pages · issued Jun 29, 2026 by Ballast Testing Laboratories · Structural
Indexed passages
page 1Placement conditions
page 3Test results
Slump measured at the point of placement ranged from 4.5 to 5.75 inches, within the specified 5 inches plus or minus 1 inch. Six cylinder sets cast. Seven day breaks averaged 3,910 psi. Twenty eight day breaks averaged 5,640 psi against the specified 5,000 psi minimum. No deficiencies noted.
Cross references
| Direction | Relation | Document | Note |
|---|---|---|---|
| this → | references | RFI-027 Hot weather placement plan for level 14 slab pour | Inspection report records compliance with the hot weather plan requirement |