Corbel

Ask the project record a question. Get the paragraph and the page, or get told the record does not say.

Corbel searches 53 indexed passages across 23 documents on Brickell Bay Tower: specifications, RFIs, submittal reviews, ASIs, inspection reports and meeting minutes. It returns passages, never summaries, and it returns nothing rather than a guess.

4 cited passages · every term of the question matched against the indexed text

Specification03 30 00Cast-in-Place Concrete5 of 5 terms

place concrete when the ambient temperature exceeds 95 degrees Fahrenheit, when the concrete temperature at the point of placement exceeds 90 degrees Fahrenheit, or when the evaporation rate calculated from ACI 305 exceeds 0.2 pounds per square foot per hour, unless the Contractor submits and the Engineer accepts a written hot weatherplacement plan for that pour. Placement between the hours of 10:00 and 16:00 during June through September shall be assumed to require such a plan

spec_033000_r1.pdf · page 14 of the documentsection 03 30 00 - 3.05Hot weather placementissued Jun 7, 2025 by Kessel Structural Engineersrevision 1
RFIRFI-027Hot weather placement plan for level 14 slab pour5 of 5 terms

written hot weather placement plan is required for this pour and must be submitted not less than five business days before placement, not 48 hours. An evaporation retarder alone does not satisfy the requirement. The plan shall address concrete temperature at the point of placement, timing of the pour, fogging

rfi_rfi_027.pdf · page 2 of the documentResponseissued Jun 26, 2026 by Quarry Ridge Concrete
Inspection reportINSP-2026-118Special inspection report, level 14 slab placement5 of 5 terms

Ambient temperature at start of placement 88 degrees Fahrenheit rising to 93 degrees Fahrenheit at 14:00. Concrete temperature at the point of placement measured between 84 and 89 degrees Fahrenheit across nine trucks. Calculated evaporation rate reached 0.21 pounds per square foot per hour between…written hot weather placement plan dated six business days before placement was on site and was followed, including fogging and immediate application of curing

insp_118.pdf · page 1 of the documentPlacement conditionsissued Jun 29, 2026 by Ballast Testing Laboratories
RFIRFI-027Hot weather placement plan for level 14 slab pour4 of 5 terms

Fahrenheit with an anticipated evaporation rate of 0.22 pounds per square foot per hour at midday. Specification 03 30 00 paragraph 3.05 requires a written hot weather placement plan where the evaporation rate exceeds 0.2. Confirm whether a plan submitted 48 hours before placement is acceptable, and whether an evaporation retarder alone

rfi_rfi_027.pdf · page 1 of the documentQuestionissued Jun 26, 2026 by Quarry Ridge Concrete

Passages are ordered by how much of the question they cover, then by cover density within the passage. Nothing above was written by Corbel; each block is the stored text of the cited page with the matched terms marked.