Change order

CO-014

Parapet raise, north elevation

co_014.pdf · 3 pages · issued Jul 7, 2026 by Vantage Construction Group · Architectural

Indexed passages

page 1Contractor position

Contractor submits that the parapet raise directed by ASI-006 constitutes additional work and requests a change in Contract Sum of 84,200 dollars and seven days of Contract Time. Contractor states the parapet was constructed to the height shown on drawing A-501 revision 1.

page 2Owner response

Rejected. ASI-006 states on its face that the change clarifies the Contract Documents and is issued at no change in Contract Sum and no change in Contract Time. Specification 07 52 00 paragraph 3.04 required a minimum 8 inch base flashing height and directed the Contractor to notify the Architect in writing before proceeding where the parapet height was insufficient. No such notice was given before the parapet was constructed. RFI-014 was submitted after the parapet was in place.

Cross references

DirectionRelationDocumentNote
this →priced byASI-006 Revised parapet detail, north elevationCO-014 submitted against ASI-006
this →referencesRFI-014 Parapet height at north elevation less than specified base flashing heightOwner response cites the timing of RFI-014