Corbel

Ask the project record a question. Get the paragraph and the page, or get told the record does not say.

Corbel searches 53 indexed passages across 23 documents on Brickell Bay Tower: specifications, RFIs, submittal reviews, ASIs, inspection reports and meeting minutes. It returns passages, never summaries, and it returns nothing rather than a guess.

7 cited passages · every term of the question matched against the indexed text

SubmittalSUB-075200-01Roofing system product data and warranty form3 of 3 terms

Returned Make Corrections Noted. The submitted warranty form is a fifteen year prorated warranty. Specification 07 52 00 paragraph 1.05 requires a twenty year no dollar limit warranty that is not prorated and does not exclude ponding water of less than forty eight hours duration. Resubmit the correct warranty form. The membrane

sub_sub_075200_01.pdf · page 1 of the documentReview actionissued Aug 31, 2025 by Juniper Roofingrevision 1
Specification07 52 00Modified Bituminous Membrane Roofing2 of 3 terms

Furnish the manufacturer's twenty year no dollar limit total system warranty covering membrane, base flashings, insulation, cover board and metal edge, commencing on the date of Substantial Completion. The warranty shall not be prorated and shall not exclude damage from ponding water of less than forty eight hours duration. Furnish…addition the roofing installer's two year workmanship warranty covering repair of leaks arising from defective workmanship, at no cost to the Owner

spec_075200_r2.pdf · page 4 of the documentsection 07 52 00 - 1.05Warrantyissued Jul 30, 2025 by Ardent Architectsrevision 2
Meeting minutesOAC-2026-31Owner Architect Contractor meeting number 312 of 3 terms

Roofing contractor confirmed the north elevation parapet raise per ASI-006 is complete between column lines 6 and 11 and that base flashing height was field verified at 8 and one quarter inches. Flood testing of roof area 3 has not yet been scheduled. Owner's representative reminded the Contractor that five…business days notice is required before each flood test under 07 52 00 paragraph

oac_031.pdf · page 2 of the documentRoofing and ASI-006issued Aug 24, 2026 by Vantage Construction Group
SubmittalSUB-075200-01Roofing system product data and warranty form2 of 3 terms

Membrane: 160 mil SBS modified bituminous cap sheet, granulated, over a 100 mil base ply, torch applied. Insulation: polyisocyanurate in two layers, 2.6 inches

sub_sub_075200_01.pdf · page 2 of the documentSubmitted productsissued Aug 31, 2025 by Juniper Roofingrevision 1
Specification07 52 00Modified Bituminous Membrane Roofing2 of 3 terms

Flood test each roof area for forty eight hours with a minimum of 2 inches of water at the high point before installation of overburden. Notify the Owner's representative a minimum of five business days before each test. Areas that fail the flood test shall be repaired and retested in full…additional cost. Written flood test reports signed by the manufacturer's field representative shall be submitted before the warranty will be accepted

spec_075200_r2.pdf · page 12 of the documentsection 07 52 00 - 3.09Flood testingissued Jul 30, 2025 by Ardent Architectsrevision 2
RFIRFI-014Parapet height at north elevation less than specified base flashing height2 of 3 terms

Specification section 07 52 00 paragraph 3.04 requires base flashing to extend a minimum of 8 inches above the finished roof surface. At the north elevation between column lines 6 and 11 the constructed parapet measures 6 and one half inches above the finished roof surface after the tapered insulation build

rfi_rfi_014.pdf · page 1 of the documentQuestionissued Jun 1, 2026 by Juniper Roofing
RFIRFI-014Parapet height at north elevation less than specified base flashing height2 of 3 terms

provide the specified 8 inch minimum base flashing height. Reduced base flashing height is not acceptable and would void the twenty year no dollar limit warranty required by 07 52 00 paragraph 1.05. See ASI-006 for the revised parapet detail and the extent of the raise. This is a design clarification

rfi_rfi_014.pdf · page 2 of the documentResponseissued Jun 1, 2026 by Juniper Roofing

Passages are ordered by how much of the question they cover, then by cover density within the passage. Nothing above was written by Corbel; each block is the stored text of the cited page with the matched terms marked.